East Stand Twickenham Rugby Stadium

Project Particulars

  • Detailed coordinated design of M & E services is 3D
  • Full public health install of 17no bar areas
  • Full public health install of 18 WC areas
  • Full public health install of 13 commercial Kitchen areas
  • Ventilation systems for commercial Kitchens
  • Ventilation systems for WC areas
  • Full ductwork distribution systems for Levels 1, 2, 2A, 3, 4 and 4a
  • New LTHW and CHW pipework distribution ranging from 100mm to 15mm
  • Install of 4-pipe fan coil system for heating and cooling of circa 210no fan coils
  • Full extension to existing BMS controls
  • Dynamic chemical flushing of pipework via use of multiple pump systems
  • Full commission of all new mechanical services across all floors
Duration:
33 weeks
Value:
£5,000,000
Area:
118,000 sq. ft

Levels 1-6, Bower Building, Old Street, London

Project Particulars

  • New LTHW and CHW pipework distribution across all floors
  • Circa 145no new 4-pipe fan coils
  • All exposed services
  • Full new ventilation ductwork distribution across each floor
  • New BMS infrastructure for all FCU’s and touch screen head end
  • Perimeter trench heating with new LTHW pipework
  • Comms room DX cooling for 24/7 operation
  • Dynamic chemical flushing of pipework via use of multiple pump systems
  • Full commission of all new mechanical services across all floors
Duration:
11 weeks
Value:
£2,400,000
Area:
65,000 sq. ft

Levels 1-4, Waterloo Station General Offices, London

Project Particulars

  • Supply and install 5no new roof mounted AHU’s
  • 4no new WC ventilation systems with roof mounted twin fans
  • 300no new internal ducted VRF units with corresponding roof mounted condensers
  • Full public heath infrastructure for new WC’s cores
  • New booster sets and water conditioners in plant room
  • New close controlled downflow N+1 cooling of 200kW for comms room
  • Gas detection systems
  • New BMS system and head end controlling all plant and on floor distribution
  • Full commission of all new mechanical services across all floors
Duration:
23 weeks
Value:
£2,800,000
Area:
75,000 sq. ft

Levels 4 & 5, 114 Whitechapel high Street, London

Project Particulars

  • Design and build for CAT B alterations to existing CAT A infrastructure across both floors
  • Relocation of 21no existing 4-pipe fan coils
  • Extensive LTHW and CHW alterations
  • New supplementary VRF systems for all meeting rooms
  • New roof mounted AHU to provide additional required fresh air
  • 120no cross talk attenuators to maintain acoustic treated air path
  • Teapoint public health installation for 4no teapoint areas
  • New 24/7 cooling for comms rooms
  • Modifications to existing BMS system
  • Chemical flushing of pipework
  • Full re-commission of systems
Duration:
16 weeks
Value:
£890,000
Area:
48,000 sq. ft

Levels 24 & 25, The Shard, London

Project Particulars

  • Design and build for CAT B alterations to existing CAT A infrastructure across both floors
  • Relocation of 18no existing 4-pipe fan coils
  • Extensive LTHW and CHW alterations
  • Ventilation adaptions with new CO2 sensors and motorized dampers to divert air to high occupancy areas when in use.
  • Teapoint public health installation for 5no teapoint areas
  • New 24/7 cooling for comms rooms
  • Modifications to existing BMS system
  • Chemical flushing of pipework
  • Full re-commission of systems
Duration:
14 weeks
Value:
£260,000
Area:
43,000 sq. ft